Section of Wildwoods Boardwalk Removed for Pump Station Project

Wildwoods Boardwalk visitors must plan an alternative route at a section near Leaming Avenue

By Shay Roddy

WILDWOOD – A section of Wildwoods Boardwalk, at Leaming Avenue, was removedclosing that section while work to complete a pump station and it’s connected outfall pipe continues.  

The section of boardwalk should be reopened no later than April 26, said Jim Oris, the city engineer in charge of the project 

The project will eliminate eight gravity outfall lines from the Wildwood beaches, in favor of one outfall hooked up to a pump station, part of a project aimed to alleviate flooding along Pacific Avenue. That new outfall should be completed June 1, Oris said.  

Construction will continue beyond Memorial Day weekend.  

On Ocean Avenue, where the contractor is working on underground pipes, work should be completed by June 9, Oris added 

Paving is scheduled to be completed June 16, and the pump station should be operational June 17, according to the engineer. 

Spout Off

Stone Harbor – Could the North Wildwood spouter tell us what kind of company he refers to that has already gotten tariff increases. Waiting for the reply spout!

Read More

Sea Isle City – Great picture of the 82nd street playground in Stone Harbor. Take note, Sea Isle, the shade provided. Maybe inquire and then just like Nike, just do it!

Read More

Most Read

Print Editions

Recommended Articles