Beach Patrol Building Moves Ahead

Stone Harbor Logo

By Vince Conti

STONE HARBOR – Stone Harbor Borough Council received an update Nov. 19 on the proposed new Beach Patrol building at 95th Street and the beach.
An earlier presentation included a design with an estimated cost of just over $4 million. The reworked design shaved $500,000 off the estimate.
It did so largely through changes to aspects of the project that sit outside or on the periphery of the building. Several council members expressed support for the modified design.
While no formal vote was taken, Business Administrator Jill Gougher was authorized to move ahead with the permitting process.
A tentative schedule for the project included a permitting and detailed design phase that would run until April or May 2020. Bids would then be solicited in June, with the expectation that an award could be made in July. Construction under the schedule would begin after Labor Day 2020, and be complete before Memorial Day 2021.

Read More

Spout Off

Cape May – As an independent who supported Democrat and Republican Presidents, I say Biden needs to step down. He doesn't have the physical and mental strength for another four years.Every time George W….

Read More

Lower Township – A Chinese car manufacturer wants to build a Chinese car factory in Mexico. I hope everybody recognizes the significance of that, but the realist in me says probably not. A proper education system in…

Read More

Cape May Court House – It's been 2 plus years since I reported a pole light out to Atlantic City Electric on their web site. I have called 3 time in those 27 months and received the same answer every time. They are…

Read More

Most Read

Print Edition

Recommended Articles

Skip to content