AVALON – The Borough of Avalon will conduct a maintenance dredging project in Pennsylvania Harbor to clear the public navigation channel in advance of the spring and summer boating seasons.
According to a release, council awarded a contract Feb.13 to Trident Piling Company, LLC that will result in largely sandy material being removed from the channel and being deposited at a location with an Acceptable Use Determination from the New Jersey Department of Environmental Protection.
A pre-construction meeting with Trident Piling Company, LLC was held Feb. 26. This project is anticipated to take five to seven days to complete.
The contractor plans to mobilize on March 25 and begin dredging on or about March 27.
“As soon as we learned from boaters that the sandy material washed in to the channel we began a survey of the conditions and began the process of obtaining necessary federal and state approvals,” stated Avalon Mayor Martin Pagliughi. “We had a very competitive bidding process and as a result saved tens ofthousands of dollars on this dredging project”.
The project will result in over 1,700 cubic yards of material to be dredged out of the harbor just west of the street end at 21st Street.
The material will be mechanically removed and placed on a barge, then in water-tight trucks to be taken to the disposal facility.
A Notice to Proceed will be issued to the contractor in the next several days.
The Avalon Borough Council included funding in the 2019 temporary budget to finance the project.
Stone Harbor – Want to be SHOCKED ? Drive to the corner of 1st and 83rd in Stone Harbor – the cinderblock foundation is higher than the neighbor’s entire first floor. This will be be biggest concrete pile in town….