Atlantic City Electric Tasks Itself with Powerline Project in Upper, Dennis

Atlantic City Electric is planning to upgrade power lines between Upper and Dennis townships to better serve customers. The new

By Press Release

MAYS LANDING – As part of its broader strategic effort to better serve customers and modernize the energy grid serving South Jersey, Atlantic City Electric is planning reliability upgrades in Cape May County to reduce the frequency and duration of outages by creating a stronger and more resilient energy grid, further enhancing service reliability for local customers. 
According to a release, construction is expected to begin in September 2021 and be completed by May 2022.
The Upper Township to Dennis Township Reliability Project includes upgrading a critical transmission line between Beesley’s Point, in Upper Township, and Ocean View, in Dennis Township, to enhance energy service reliability for thousands of customers. 
The company is replacing the existing lattice transmission tower structures with new, stronger steel transmission poles prepared to handle more extreme weather and reduce the impacts of severe storms.
If residents have questions or would like additional information, they can contact Atlantic City Electric, at 888-530-2047, or UpperTwp-DennisTwpReliability@exeloncorp.com.

Spout Off

North Cape May – Hello all my Liberal friends out there in Spout off land! I hope you all saw the 2 time President Donald Trump is Time magazines "Person of the year"! and he adorns the cover. No, NOT Joe…

Read More

North Cape May – "For unto us a Child is born, unto us a Son is given.” — from Handel’s “Messiah”

Read More

Cape May County – These drones are making the hair on the back of my neck stand up. Eyewitness accounts say they are loud, very large, and obviously not available on Amazon. I just read an interview with a drone…

Read More

Most Read

Print Editions

Recommended Articles

Skip to content