Strathmere Improvements Near Completion

UT Logo

By Camille Sailer

PETERSBURG – Upper Township Engineer Paul Dietrich told Upper Township Committee members Jan. 13 that long-awaited Strathmere improvements are on schedule, and will be completed soon.
“The pouring of concrete on Commonwealth Avenue will be done this week, and the grading and paving by the end of the month,” said Dietrich. “We also are expecting the delivery around mid-February of the two bulkheads we’ve been expecting, and these then will be installed, so we meet proper height requirements.
“We’ve been very fortunate with the mild weather, so we’re happy that these projects that Strathmere residents have been hoping for finally are nearing completion.”

Spout Off

Wildwood – So Liberals here on spout off, here's a REAL question for you.
Do you think it's appropriate for BLM to call for "Burning down the city" and "Black Vigilantes" because…

Read More

North Cape May – Let's put out some facts about EV's and the EV school bus's that Biden was promoting. An EV School bus cost $375,000. Per Bus. The same Diesel Bus is $187,000. Now, guess what…?…

Read More

Sea Isle City – The amount of people who do not stop for pedestrians is astounding. I was halfway across in a marked crosswalk and almost got run over on Landis Ave.

Read More

Most Read

Print Editions

Recommended Articles

Skip to content