STONE HARBOR – Stone Harbor Administrator Jill Gougher provided borough council with a tentative construction schedule of a new Beach Patrol building.
Gougher said the assessment phase was underway and would be completed this year. Conceptual and final design phases would be part of the 2019 capital budget and should be completed in the calendar year. Construction of a facility is estimated to be about a six-month job and would be funded in the 2020 capital budget.
At this stage, all schedules are estimates, and capital funding has not been approved.