AVALON – The replacement or upgrade of over 6,500 Avalon water meters is moving to a bid process tentatively scheduled for April.  

Borough Engineer Thomas Thornton provided the governing body with a proposed schedule, at the Feb. 10 Avalon Borough Council meeting. 

The schedule calls for initiating the bid process in April, making an award in June, completing preparatory technology infrastructure work over the summer, and beginning the installation of new meters as soon as summer ends. A likely completion date is February 2022, Thornton said. 

The project was rejuvenated when the borough contracted Mott MacDonald for the development of the technical specifications that drive contractor bidding.  

The borough’s water system management firm, Middlesex Water Company, did not have the expertise in specification development for Advanced Metering Infrastructure (AMI) technology. 

The project calls for the installation of meters that use radio frequency transmission to continuously upload usage data to support water system monitoring, customer information access, and interface with appropriate billing software. 

Spout Off

Cape May County – It is painfully obvious that most of those who submit a political Spout is either: Misinformed, spew baseless conspiracy theories or give emotional opinions. And those who comment online? They are…

Read More

North Cape May – Re: The Whitesboro comment on your debate watch party tomorrow evening and along with your meal you may add some "honeydew felons". While you are at it, bring some feed for the "…

Read More

North Cape May – Re: The Del Haven comment on our former president calling our deceased military members, "suckers and losers". Hmm. Once again, the fake media doing their thing to destroy a good president…

Read More

Most Read

Print Editions

Recommended Articles

Skip to content