AVALON – Avalon Borough Council heard a report on a final change order adjustment for the completed reconstruction and repair of the Eighth Street jetty. The jetty was severely damaged...
AVALON – Avalon Borough Council heard a report on a final change order adjustment for the completed reconstruction and repair of the Eighth Street jetty. The jetty was severely damaged...
AVALON – Avalon’s north end drainage project was set to move to the final design. The estimated $9.5 million effort was intended to relieve serious flooding in the borough’s low-lying...
AVALON – Under almost all circumstances, normal practice is that public construction projects are completed before Independence Day, or they are stopped and resumed in the fall. The Eighth Street...
AVALON – Damage to the Eighth Street Jetty, from Winter Storm Jonas, in 2016, is more extensive than originally thought, despite Avalon officials’ efforts to analyze the necessary repairs. Restoration...