Middle to Finish Subdivisions

MT Logo

By Vince Conti

BURLEIGH – Three subdivisions along Route 9 adjacent to the land occupied by The Lighthouse Church have each defaulted on obligations to complete improvements required when they gained site approval for the developments. The developers in default are Chazry Builders Inc. and Ros-Len Inc.
At its June 4 meeting, Middle Township Committee adopted a resolution authorizing the municipality to complete the work and seek payment from the developers’ bonds. 
Township Engineer Vincent Orlando said the work remaining was largely confined to the final asphalt for the roads. 
“There may be a few other small items,” he said. Orlando assured committee that the bond funds should be adequate to cover the remaining work.

Spout Off

Wildwood Crest – Several of Donald Trump’s Cabinet picks have created quite a bit of controversy over the last few weeks. But surprisingly, his pick to become the next director of the FBI hasn’t experienced as much…

Read More

Stone Harbor – We have a destroyer in the red sea that is taking down Drones. You have to track them to down them, how come we can't see where the drones on the east coast are from? Are we being fools when the…

Read More

Cape May County – Dear friends of Cape May County, We would like to wish a joyous Christmas and happy holiday season to you and yours; from our family! We would also like to implore you to properly secure your…

Read More

Most Read

Print Editions

Recommended Articles

Skip to content