Stone Harbor/Avalon Beach Fill Update

By Press Release

STONE HARBOR – Officials from Avalon and Stone Harbor attended the weekly progress meeting for the upcoming beach fill project at the Stone Harbor Firehouse Feb. 2.
In attendance from Stone Harbor were Council President Karen Lane, Council members Joselyn Rich and Ray Parzych, Business Administrator Jill Gougher, Public Works Director Grant Russ, and Engineer Marc DiBlasio.
In attendance from Avalon were Business Administrator Scott Wahl and Engineer Steve Morey from Mott MacDonald. Representatives from the United States Army Corps of Engineers, state Department of Environmental Protection, and Great Lakes Dredge and Dock Company, LLC were also in attendance.
The dredge “Texas” will be finishing up some emergency work in the Christiana River likely by Feb. 5. Once that work is completed, the “Texas” will make its way to Hereford Inlet near Stone Harbor to begin the actual beach fill work. The anticipated start date of the actual dredging is Feb. 12. The project will begin in Stone Harbor and pump sand from Hereford Inlet from the south end of Stone Harbor to 105th Street. Then, the dredge will be mobilized to Townsend’s Inlet to conduct a major beach fill project in Avalon anticipated to run from 9th Street to the northern limits of 38th Street.
Stone Harbor’s initial portion of the project is anticipated to place 390,000 cubic yards of sand on the borough’s beachfront. Some additional federal emergency funding is likely going to be awarded that will be placed on the northern Stone Harbor beaches from 80th Street to 105th, along with Avalon’s beaches from 76th Street to 80th Street. That will occur after the major Avalon beach fill and is dependent on a reasonable quote from Great Lakes Dredge and Dock Company; a quote for the work is expected in the coming days and will be presented to the United States Army Corps of Engineers. If awarded that would place an additional 320,00 cubic yards of sand on Stone Harbor beaches.
A significant amount of heavy equipment will be arriving over the next couple of weeks, including the “Texas”. A crew boat called “Swift Runner” will be arriving in Stone Harbor in the next few days. Various bulldozers, excavators, anchor barges, etc. are arriving in Stone Harbor for the project. When Avalon’s portion of the project begins, the likely staging areas for equipment will be near the 8th Street Jetty on the beach, and some equipment may be stored at the vehicular beach access path at 32nd Street, on the beach. Avalon has asked Great Lakes not to use the northerly parking lot on the north side of Community Hall since it was recently repaved.
Approximately 1.3 million cubic yards of sand will be removed from Townsend’s Inlet during this project, with much of the sand being dedicated to the Avalon portion of the project, and the remaining sand to be used for the northerly limits of Stone Harbor’s beach fill. There is adequate sand in Townsend’s Inlet to complete all of these projects.
Various surveys and required documents have been completed to prepare this beach fill for launch. Surveys have been taken of the beaches following the nor’easter that visited both communities early last week.

Spout Off

Wildwood – So Liberals here on spout off, here's a REAL question for you.
Do you think it's appropriate for BLM to call for "Burning down the city" and "Black Vigilantes" because…

Read More

North Cape May – Let's put out some facts about EV's and the EV school bus's that Biden was promoting. An EV School bus cost $375,000. Per Bus. The same Diesel Bus is $187,000. Now, guess what…?…

Read More

Sea Isle City – The amount of people who do not stop for pedestrians is astounding. I was halfway across in a marked crosswalk and almost got run over on Landis Ave.

Read More

Most Read

Print Editions

Recommended Articles

Skip to content