SEA ISLE CITY — Great Lakes Dredging Company completed beach fill operations on Sun., June 13.
According to an alert from the city, beaches from 73rd Street – 94th Street received 800,000 cubic yards of sand and are now open to the public.
The total project cost $6.6 million, with the State of New Jersey committing to pay 75 percent and the City of Sea Isle City responsible for paying the remaining 25 percent of the total cost
Expect to see equipment clean up and de-mobilization over the next few days.