93rd Street Pump Station Construction Could Begin in ’22

Laying

By Vince Conti

STONE HARBOR – Thomas Thornton, of Mott MacDonald, presented an update on the 93rd Street stormwater pump station project to Stone Harbor Borough Council Feb. 1.  

Thornton said he hoped that a construction contract can be awarded by July, with a “notice to proceed” in August. If that schedule holds, the project completion date would be January 2024. 

The wildcard in that schedule is the completion of the permitting phase by the end of April, which depends upon necessary approvals from the state Department of Environmental Protection (DEP) and the U.S. Army Corps of Engineers.  

Necessary documentation has been submitted to both agencies, Thornton said, with a response from the Army Corps in hand and no response yet from the DEP. Mott stands ready to respond to the questions and concerns raised by either agency. 

The stormwater pump station at 93rd Street will be among the largest capital projects the borough has undertaken and is an essential element of the flood mitigation strategy. Its intended drainage area runs from 89th Street to 97th Street and from Third Avenue to the bay. 

Spout Off

Wildwood – So Liberals here on spout off, here's a REAL question for you.
Do you think it's appropriate for BLM to call for "Burning down the city" and "Black Vigilantes" because…

Read More

North Cape May – Let's put out some facts about EV's and the EV school bus's that Biden was promoting. An EV School bus cost $375,000. Per Bus. The same Diesel Bus is $187,000. Now, guess what…?…

Read More

Sea Isle City – The amount of people who do not stop for pedestrians is astounding. I was halfway across in a marked crosswalk and almost got run over on Landis Ave.

Read More

Most Read

Print Editions

Recommended Articles

Skip to content